Gainesville Logo
 
File #: 120442.    Version: Name:
Type: Discussion Item Status: Passed
File created: 10/8/2012 In control: City Manager
On agenda: 11/1/2012 Final action: 11/1/2012
Title: Bid Award - Depot Park Phase II Pond and Pump Station Project (B) This is a request for the City Commission to authorize the bid award in the amount of $5,191,900 to R.E. Arnold Construction, Inc., for the Depot Park Phase II Pond and Pump Station project.
Attachments: 1. 120442A_PPT_20121101.pdf, 2. 120442B_Bid Tab_20121101.pdf
Title
Bid Award - Depot Park Phase II Pond and Pump Station Project (B)

This is a request for the City Commission to authorize the bid award in the amount of $5,191,900 to R.E. Arnold Construction, Inc., for the Depot Park Phase II Pond and Pump Station project.

Explanation
On July 25th, the City Purchasing Division solicited bids for the Depot Park Phase II Pond and Pump Station project. Four (4) firms responded with bids. R.E. Arnold Construction, Inc. was the lowest responsible and responsive bidder in the amount of $4,514,696.99. The scope of this contract includes the Pump Station located east of SE 4 Street along Sweetwater Branch, the dewatering and construction of the pond and associated walls, lining and piping, the two foot clean soil cap over the site, and wetlands mitigation planting.

R.E. Arnold Construction, Inc. is also the lowest and responsive bidder for the NW 22 Street project that was subsequently bid. Staff held a meeting with R.E. Arnold Construction to determine whether they had the capacity to deliver services on both projects simultaneously. R.E. Arnold representatives presented a plan to staff that adequately demonstrated their intended approach to delivering both projects.

The Depot Park project has been a collaborative project between GRU, Public Works and CRA for a number of years. GRU’s primary responsibility has been associated with the coal tar and related remediation efforts; Public Works has been responsible for the development of the stormwater management aspects and agreed to manage the arsenic remediation for the site. CRA has been responsible for the park components as well as the Depot Historic Building renovation work and coordination with the Cade Museum. Through all phases of this transformational project the three entities have worked closely to ensure that all aspects were being coordinated and issues identified and addressed as efficiently as possible. Due to the complexity of the project there has had t...

Click here for full text



© 2014 City of Gainesville, Florida. All right reserved.

CONTACT US
City Departments
Online Contact
200 East University Ave.
Gainesville, FL 32601
352-334-5000