File #: 060583.    Version: 0 Name: Thirteenth Amendment to the Contract for Professional Consulting Services for the East Gainesville Sprout Project (B)
Type: Staff Recommendation Status: Passed
File created: 10/23/2006 In control: City Manager
On agenda: Final action: 10/23/2006
Title: Thirteenth Amendment to the Contract for Professional Consulting Services for the East Gainesville Sprout Project (B) This item involves a request for the City Commission to approve additional services and compensation for consulting services for the East Gainesville Sprout Project in the amount of $263,196.00.
Attachments: 1. 060583_200610231300.PDF
Title
Thirteenth Amendment to the Contract for Professional Consulting Services for the East Gainesville Sprout Project (B)
 
This item involves a request for the City Commission to approve additional services and compensation for consulting services for the East Gainesville Sprout Project in the amount of $263,196.00.
 
Explanation
This amendment is for additional work by Environmental Consulting Technology, Inc. related to the "Depot Park" project for the Phase I - Remediation, site analyses, development plans and specifications and other services for Phase 2 remediation and construction.  This amendment is necessary to adjust the budget for professional services to include work completed to date and allow for completion of a variety of tasks.  The attached Cost Distribution Table between the City's Stormwater Services Division (COG) and Gainesville Regional Utility's Gas Department (GRU) presents the individual tasks, the budget adjustments, each funding source share and is accompanied by justification statements for each task.
 
Fiscal Note
The additional services are to split between GRU-Gas Utility and the COG-Stormwater Utility in the amounts of $246,196 and $17,000, respectively.  Funding for the remediation is included in the Gas Acquisition Cleanup within the Capital Improvements Budget for FY2006.  This is funded through the Cost Recovery Factor charged to all Gas System Customers.  Funding for the Stormwater work is available from the State Revolving Fund loan obtained for the project.
 
Recommendation
Recommended Motion:  The City Commission:  1) accept the additional work described for the project; 2) authorize the City Manager to execute the Thirteenth Amendment to the contract for Professional Consulting Services for the East Gainesville Sprout Project, subject to approval by the City Attorney as to form and legality; and 3) authorize the City Manager to issue a modified purchase order in the amount not to exceed $2,559,863.
 
 
 