Title: Reimbursement for Oversizing of Water and Wastewater Facilities at Hailey Forest Condominiums (B) Reimburse the developer of Hailey Forest Condominiums for the oversizing of W/WW facilities.
Attachments: 1. 060180_20060626.pdf
Title
Reimbursement for Oversizing of Water and Wastewater Facilities at Hailey Forest Condominiums (B)

Reimburse the developer of Hailey Forest Condominiums for the oversizing of W/WW facilities.
Explanation
Hailey Forest is a single family condominium development located at 4823 SW Archer Road. A wastewater gravity collection system, pump station and force main must be constructed to provide wastewater service for the project. The pump station and force main will connect to an existing 36" force main located in the southern right-of-way of SW Archer Road. Hailey Forest must also construct a potable water distribution system to serve the development with domestic water.

In order to properly serve adjacent undeveloped parcels and minimize the need for multiple lift stations that GRU would have to operate and maintain, oversizing of the pump station wetwell and increased depth of the gravity collection system is required. For the same reason, water and wastewater stubouts to the property line are being made. Additionally, the force main is being oversized to increase wastewater system capacity and reliability. The Developer's Engineer has accommodated this in the development design. GRU's incremental cost to oversize the force main, deepen the gravity wastewater system and stubout wastewater service is $23,303. GRU incremental cost for the developer to provide two potable water stubouts is $8,853.

The recommended amount of $32,153 includes all construction labor and materials associated with the water and wastewater system oversizing to satisfactorily complete the work.
Recommendations
The City Commission authorize reimbursement to the Developer of Hailey Forest Condominiums, Pleiman Homes, Home Technology Construction Inc., for the oversizing of the water and wastewater facilities in an amount not to exceed $32,153.
Fiscal Note
Monies for this project are available in the FY 07 Water and Wastewater Capital Improvements Budget.
Draft...

Click here for full text



© 2014 City of Gainesville, Florida. All right reserved.

CONTACT US
City Departments
Online Contact
200 East University Ave.
Gainesville, FL 32601
352-334-5000