Title:
|
Manhole and Conduit System for Downtown Underground Phase IX (B)
|
Title
Manhole and Conduit System for Downtown Underground Phase IX (B)
Explanation
In order to continue the Commission authorized project to underground electric utilities in the downtown area, conduits and manholes must be installed along SW 12th Street from SW 4th Avenue to the unit block of NW 12th Street.
Invitations to Bid were sent to five (5) prospective bidders from which two responses were received of which one (1) no-bid was received. A tabulation of the bid received is attached for your reference.
The not to exceed amount includes $21,000.00 contingency allowance for handling unmapped water, sewer, telephone and gas lines and any other unforeseen conditions.
Recommendations
The City Commission approve the issuance of a purchase order to Robert L. Dollar, d.b.a. Dollar and Son Trenching, Plumbing & Electric, for the installation of electric system manholes and conduit for Phase IX of the Downtown Underground Project in an amount not to exceed $233,586.00.
Fiscal Note
Funds to this project have been provided for in the FY '97-'98 Utilities budget.
Drafter
Prepared by H. Reid Rivers, Manager, Energy Delivery Engineering
Submitted by Michael L. Kurtz, General Manager for Utilities