Title
Sixth Street Corridor Rail Trail Project - 30% Design Presentation (B)
This item involves a presentation by the Public Works engineering staff on the Sixth Street Corridor Rail Trail, which is currently at the 30% design stage.
Explanation
The Sixth Street Corridor Rail Trail project is underway after many years of delay while waiting for the State of Florida to purchase the associated abandoned CSX railroad rights-of-way. This presentation is intended to inform the City Commission of the design progress on this project as well as present the design intent and projected direction, including the current project schedule.
Fiscal Note
There is no fiscal impact to the City of Gainesville at this time.
Recommendation
Recommended Motion: The City Commission: 1) hear the staff presentation; and 2) take action deemed appropriate.