File #: 120355.    Version: 0 Name: Amend the Capital Improvement Plan and increase funding for the Centralized Garage Project (B)
Type: Discussion Item Status: Passed
File created: 9/20/2012 In control: City Commission
On agenda: 9/20/2012 Final action: 9/20/2012
Title: Amend the Capital Improvement Plan and update the budget for the Centralized Garage Project (B) This is a request for the City Commission to approve amendment of the Capital Improvement Plan and update the budget for the Centralized Garage Project.
Attachments: 1. 120355_Garage PPT_20120920.pdf
Title
Amend the Capital Improvement Plan and update the budget for the Centralized Garage Project (B)

This is a request for the City Commission to approve amendment of the Capital Improvement Plan and update the budget for the Centralized Garage Project.

Explanation
In 2002, a team from General Government and GRU did a comprehensive study on the best option from an efficiency and financial standpoint to replace the 5th Avenue Garage Facility. Based upon this study, it was determined a centralized garage facility would be the most cost effective and efficient for the City/GRU. This original facility concept was intended to generate operational savings by replacing the existing separate fleet repair facilities located at NW 39th Avenue and SW 5th Avenue, however neighbors raised concerns about expanding operations at the Public Works Complex. After much public input on the Centralized Garage concept, the City Commission denied the staff recommendation to expand the garage at the existing site and authorized staff to begin searching for another site. On August 21, 2008, the City Commission ranked the JDF Logistics property (78.37 acres) as the number one site to co-locate the Centralized Garage Project.

There have been no increases to the budget for this project since the City Commission approved funding as part of the FY09 - FY13 Capital Improvement Plan in May, 2008. At the time the cost of such a combined facility was estimated at approximately $9.6 million, and subsequently the City Commission appropriated $9,610,000 for property acquisition and construction of a Centralized Garage facility. This project is funded 50% through Fleet Replacement Fund monies and 50% from Gainesville Regional Utilities.

To date, property has been identified and acquired, an architect has been hired and has completed the building designs, and in January of 2012 Parrish-McCall was hired to provide construction management services for the garage facility. As Parrish-McC...

Click here for full text