Title: SW 62nd Boulevard Update (B) This is a request for the City Commission to hear an update on the 4-lane extension for SW 62nd Boulevard. **ESTIMATED STAFF ORAL PRESENTATION 5 MINUTES**
Attachments: 1. 150860_MAP_20160407.pdf
Title
SW 62nd Boulevard Update (B)

This is a request for the City Commission to hear an update on the 4-lane extension for SW 62nd Boulevard. **ESTIMATED STAFF ORAL PRESENTATION 5 MINUTES**


Explanation
In October of 2015 the MTPO prioritized the construction of a 4-lane SW 62nd Blvd extension between SW 20th Ave and SW 43rd St as the top priority project under the Surface Transportation Program (STP), and allocated up to $9 million towards the project. Funds may be available between FY21- FY25. The cross-section for the project was adopted by the MTPO in 2008, including provisions for bicycle, pedestrian and transit facilities; the project also includes a 4-lane bridge over Hogtown Creek.

Working with FDOT staff to identify potential opportunities for constructing this project in phases, they have recommended moving forward with a two-lane project in Segment B to fill in the gap between Clark Butler Boulevard and the current end of the 62nd Street just south of SW 20th Avenue. Under this option the full right of way width would be acquired along this segment. The estimated cost for a two-lane with full bridge alternative is approximately $20 million plus right of way cost. The estimated cost of a two-lane phased bridge alternative is $12 million plus right of way cost.

FDOT has two funding opportunities: the Transportation Regional Incentive Program (TRIP) with $3,000,000 available for the district, and the County Incentive Grant Program (CIGP) with $4,000,000 available for the district. Both funding opportunities require a match. The funds would be available in FY21 and could be combined with STP dollars.

In March 2016 the US DOT announced a new cycle of the TIGER grant, and a FASTLane grant opportunity. SW 62nd Blvd may be eligible for the FASTLane grant as a “small” project, which allows for the funding of pre-construction activities, such as acquisition of right-of-way; the application is due on 04/14/2016. The TIGER grant requires that the project...