NW 1st Avenue Streetscape: Project Update (B)
Explanation
NW 1st Ave, between NW 16th St and NW 20th St, is an important mixed-use corridor located a block away from the University of Florida and the Ben Hill Griffin Stadium. The NW 1st Ave Streetscape project has been a top priority Community Initiative for the College Park / University Heights (CPUH) redevelopment area, and is part of the District’s approved work plan and budget for FY15-16.
Since 2012, the project team has been extensively involving the local community in the project development. Through stakeholder engagement, the design team developed a desired scope of improvements and created a conceptual street layout. 15% and 50% Construction Documents sets were approved by the CRA Board in April and September 2014, respectively. In November 2015, CRA Boards approved engineering and design contracts to complete the design and permitting for the full scope of the project, including two separate efforts: NW 1st Ave Project 1: Underground Infrastructure and Roadway Improvements, and NW 1st Ave Project 2: Utility Conversions and Streetscape Improvements. In 2016, the project team has been coordinating with stakeholders to finalize the proposed design, including holding four stakeholder meetings dedicated to each of the four project blocks, numerous one-on-one stakeholder meetings, and many cross-departmental meetings with City staff.
To complement the physical impact of the streetscape project and to support local businesses, CRA staff developed a draft marketing and communications plan and three time-limited façade improvement incentive programs for the Midtown area. These proposed plans were presented to forty property and business owners at a Stakeholder Meeting that took place on June 29th. At today’s meeting, staff will present these proposed programs to the CRA Board, for discussion and approval.
Fiscal Note
An amount of up to $40,000 will be dedicated to the Midtown Architectural Assis...
Click here for full text