Title: Design and Construction of Fire Station 1 Update (B) This item recommends that the City Commission review and approve the 30% drawings for Fire Station 1 at 525 South Main Street, waive the review at 60%, and receive a presentation at final completion of the drawings.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Design and Construction of Fire Station 1 Update (B)

This item recommends that the City Commission review and approve the 30% drawings for Fire Station 1 at 525 South Main Street, waive the review at 60%, and receive a presentation at final completion of the drawings.

Explanation
This item brings to the City Commission an update on the new Fire Station 1 project and review of construction drawings of the architect and engineers at 30% of completion. Current administrative policy directs Commission approval of construction drawings at 30%, 60%, and final completion respectively. Construction drawings are used by the Construction Manager-at-Risk to provide the City Commission cost of construction estimates. As additional funds will be needed, the accuracy of the estimates is important to the Commission’s deliberations on funding of the project.

A capital request submitted in FY 2010 received approval to start the project with $6 million in FY 2015. A later modification advanced 10% for design and additional funding for land acquisition of $1.2 million which was applied from SAFER Grant savings in FY 2013.

On August 15, 2013, the City Commission authorized the purchase of properties located in the 500 block of South Main Street for construction of a new facility for Fire Station 1.

On June 5, 2014, the Commission approved the ranking for design services for Fire Station 1 and, on February 5, 2015, approved the ranking of firms for Construction Management at Risk.

Bentley Architects & Engineers was chosen for the project with Commission direction regarding urban structure, fire rescue response and function, and a LEED building approach.

Neighborhood and stakeholder meetings were held at the beginning of the project and to review the preliminary design. Key consideration for this design includes its presence and role as a signature building in the South Main Street redevelopment, Depot Park, and gateway to the proposed Power District plan.

On De...

Click here for full text



© 2014 City of Gainesville, Florida. All right reserved.

CONTACT US
City Departments
Online Contact
200 East University Ave.
Gainesville, FL 32601
352-334-5000